Financing agreement confirmed for Crossrail project

550

The Mayor of London, Transport for London (TfL), the Department for Transport (DfT) and HM Treasury have confirmed a funding and financing package for the final phase of the Crossrail project.

Crossrail Ltd announced in August that it expected the Elizabeth line to open through central London in the first half of 2022 and that they would require funding beyond the agreed funding envelope.

The shortfall will initially be covered by the Greater London Authority (GLA) borrowing up to £825m from the DfT which will be given by GLA to TfL as a grant.

The GLA will repay this loan from Business Rate Supplement (BRS) and Mayoral Community Infrastructure Levy (MCIL) revenues.

Sadiq Khan said: “Securing this financing package enables us to press full steam ahead with getting the central section of the Elizabeth line open as soon as possible.

“The Government have insisted London must pay the shortfall – despite the overwhelming majority of the tax income that will result from Crossrail going to the Treasury. This is another example of London supporting the country way over and above the help we get from this government.

“I do not want this project to be stalled so it is vital that we dig deep to get the railway up and running. I will continue to monitor progress closely and do everything I can to minimise costs – helping ensure London and beyond can enjoy its many benefits sooner rather than later.”

news london

NOW READ: City of London workers probed on post-Covid leisure and travel

Governance of Crossrail transferred directly to TfL in October, helping to simplify responsibilities and ensure decision making is seamless and fully aligned at this crucial stage.

A special purpose committee of the TfL Board, the Elizabeth Line Committee, provides high-level oversight of the project, the first meeting took place last week. The project remains a jointly sponsored by TfL and the DfT and an independent DfT representative will attend the committee meetings.

Mark Wild, Chief Executive, Crossrail Ltd, said: “Delivery of the Elizabeth line is now in its complex final stages. Good progress continues to be made with completing the remaining infrastructure works so that we begin intensive operational testing, known as Trial Running, at the earliest opportunity in 2021.

“Many of the stations are now nearing completion and we will shortly commence an enabling phase for Trial Running which allows testing in the tunnels to be undertaken with an increased number of trains, further helping to build operational reliability.

“We are doing everything possible to deliver the Elizabeth line as safely and quickly as we can.”

When fully open, the Elizabeth line will increase central London’s rail capacity by 10%, able to carry more than half a million passengers per day and will support new journeys through central London out to Essex and Berkshire.

The new railway is expected to boost the UK economy by £42 billion.

For the latest headlines from the City of London and beyond, follow City Matters on TwitterInstagram and LinkedIn.